How Public Parking Group Transformed NYC Garages with EV Charging Stations
How Source Forward Helped Public Parking Group Transform NYC Garages with EV Charging Stations
As electric vehicles (EVs) gain traction, parking facilities face growing expectations to provide charging options for EV drivers. Public Parking Group, managing multiple parking garages across New York City, recognized this need but was unsure how to move forward with EV charging station installation without disrupting their core business of parking management.
To navigate this challenge, they partnered with Source Forward and DVM Industries to design and install commercial EV charging stations across four pilot locations, setting the stage for future rollouts.
The Challenge
Public Parking Group needed to modernize their facilities by integrating EV charging stations, but the project posed several hurdles:
- Operational Compatibility: Charging infrastructure needed to align with their current parking operations, ensuring minimal disruption to business.
- Technical Complexity: Installing EV chargers required significant electrical upgrades, meeting local regulations, and coordinating with utilities for permitting and compliance.
- Cost Management: With EV charger installation costs exceeding $900,000, securing incentives was necessary to offset expenses and make the project financially viable.
- Long-term Usability: The chargers needed to be durable, user-friendly, and equipped with advanced software for monitoring usage and collecting payments.
Public Parking Group needed a reliable partner with the expertise to tackle these challenges while delivering a scalable solution for their portfolio.
The Solution
Source Forward and DVM Industries provided a comprehensive solution, handling every aspect of the project from initial consultation to installation. Here’s how the team delivered results:
1. Tailored Planning and Design
Source Forward and DVM Industries began by discussing with Public Parking Group’s team to understand their operational priorities and needs. This informed a custom plan to integrate EV chargers seamlessly without disrupting parking operations. The plan included:
- Designing 10 EV charging stations at each location.
- Creating a layout optimized for traffic flow and convenience.
2. Regulatory and Technical Expertise
The team leveraged its in-house engineering staff to handle all technical and regulatory requirements, including:
- Coordinating with local municipalities for permitting.
- Submitting PE-stamped electrical drawings and site plans.
- Ensuring compliance with all utility requirements.
3. Turnkey Installation
Source Forward furnished and installed all components, including upgraded switch gear, conduit, panels, and electrical connections. The project also included site work like trenching, line striping, and signage.
4. Maximizing Incentives
Source Forward managed all rebate paperwork, securing $846,000 in incentives to offset the project’s $940,000 cost. This reduced the net expense to just $94,000, which was a significant savings for Public Parking Group.
Results
Public Parking Group’s pilot project was a resounding success. Here are the key highlights:
- Number of Chargers Installed: 40 (10 per garage)
- Total Project Cost: $940,000
- Incentives Secured: $846,000
- Net Project Cost: $94,000
The project provided cutting-edge EV charging capabilities, and also established a blueprint for scaling across Public Parking Group’s other locations. By working with Source Forward and DVM Industries, they now have an operational model that balances tenant needs with profitability.
Moving Forward
Public Parking Group is already planning to expand EV charging infrastructure across more of their locations, using the lessons learned and the systems established during this pilot project. With Source Forward and DVM Industries’ guidance, they are well-positioned to meet the growing demand for EV charging stations while maintaining efficient parking operations.
Why Choose Source Forward
Source Forward and DVM Industries’ combined expertise in EV infrastructure made all the difference for Public Parking Group. From design and permitting to installation and incentives, the team delivered a seamless experience. If your property could benefit from EV chargers, Source Forward is here to help you make it happen—efficiently, affordably, and sustainably.